SaskPower invests to support demand growth, renew aging grid
REGINA, Saskatchewan -- - SaskPower made significant investments - $1.279 billion - into the provinceÂ’s electrical grid in 2014, as aging infrastructure, increasing demand and changing environmental regulations continue to challenge the Crown corporation.
SaskPower tabled its 2014 Annual Report in the Saskatchewan Legislative Assembly today, reporting an operating income of $43 million in 2014 on over $2 billion in revenue.
“Our province is focusing on investing in infrastructure to keep our province strong, and that includes our electrical grid,” Minister Responsible for SaskPower Bill Boyd said. “Those investments do have an impact on SaskPower’s annual income, but they are necessary to renew and improve the system and meet increasing demand for electricity in our growing province.”
“Like many electrical utilities, SaskPower is continuing to operate in a challenging environment,” said President and CEO Mike Marsh. “Demand for electricity has grown nearly 10 per cent in just two years, and our peak demand continues to break records. It’s critical that we invest in renewing and maintaining our system so that we are positioned to supply reliable, affordable and sustainable power today and into the future.”
Key SaskPower highlights from 2014 include:
- $409 million to upgrade power stations
- $583 million to connect customers to the system, as well as transmission and distribution upgrades
- The successful launch of the Boundary Dam carbon capture and storage project, the first of its kind in the world
- Construction continued on the Shand Carbon Capture Test Facility, scheduled to be completed in 2015
- Work continued on the expansion of the Queen Elizabeth Power Station in Saskatoon, which will add 205 megawatts to the grid when complete in 2015
- Work on the $380 million I1K transmission line, which will run from Island Falls to Key Lake to serve industry and improve reliability in the provinceÂ’s north
- SaskPower reached an agreement with Manitoba Hydro to import 25 MW of power from 2015 to 2022
Related News

Covid-19 puts brake on Turkey’s solar sector
ANKARA - The decision by the Turkish Energy Market Regulatory Authority to halt part of the system of processing net metering applications risks bringing the only vibrant segment of the nation’s solar industry to a grinding halt.
The regulator has suspended monthly meetings of the committee which makes technical evaluations of net metering applications, citing concerns about the spread of Covid-19.
The availability of electricity bill credits for net-metering-approved households which inject surplus power into the grid has seen the rooftop projects the scheme is typically associated with remain the only source of new solar generation capacity in Turkey of late.
However the…