AECL provides update on NRU activities

subscribe

Atomic Energy of Canada Limited (AECL) provides the following status report on the unplanned shutdown of the NRU reactor at its Chalk River Laboratories.

AECL reports that removal of the last NRU fuel rod was successfully completed June 15. Removal of the remaining 15 control, adjuster and cobalt-60 isotope rods has begun. Seven of these assemblies were removed from the reactor as of June 16.

Completion of rod removal and the subsequent removal of heavy water from the reactor is expected to be complete by the end of this month. Final preparations are underway to conduct a detailed inspection of the condition of the reactor vessel using remote non-destructive examination techniques. This task will be performed as soon as the remaining rods and heavy water have been removed.

AECL is drawing on advice provided by its technical staff and industry experts to determine the most effective options for vessel repairs. AECL continues to work with industry experts on cleaning, inspection and repair techniques for the reactor vessel. Earlier this week, AECL was provided with a demonstration of a potential repair technique from a supplier company. Evaluation of this and other inspection, cleaning and repair options continues.

A full-scale mock-up of a portion of the NRU vessel is currently being constructed at Chalk River. This mock-up will serve to provide on-site testing and training of vessel inspection and repair work.

The NRU heavy water leak rate has been reduced to a flow of between 3-4 kg/hr. A small portion of the leakage evaporates and results in a monitored airborne tritium release through the NRU reactor ventilation system. While this airborne tritium release remains about 1/1,000 of the regulatory limit, the action level for tritium release to the atmosphere was exceeded this week due to the leak.

AECL confirms that there is no threat to workers, the public, the environment or nuclear safety related to this event. AECL will continue to provide updates to the CNSC and stakeholders when new information becomes available.

Related News

ford-cancels-wind

Doug Ford ‘proud’ of decision to tear up hundreds of green energy contracts

TORONTO - Ontario Premier Doug Ford said Thursday he is “proud” of his decision to tear up hundreds of renewable energy deals, a move that his government acknowledges could cost taxpayers more than $230 million.

Ford dismissed criticism that his Progressive Conservatives are wasting public money, telling a news conference that the cancellation of 750 contracts signed by the previous Liberal government will save cash.

“I’m so proud of that,” Ford said of his decision. “I’m proud that we actually saved the taxpayers $790 million when we cancelled those terrible, terrible, terrible wind turbines that really for the last 15 years have…

READ MORE
hydro one logo

Ontario's electricity 'recovery rate' could lead to higher hydro bills

READ MORE

bc hydro sign

BC Hydro rates going up 3 per cent

READ MORE

phone pad

Shocking scam: fraudster pretending to be from BC Hydro attempts to extort business

READ MORE

iran nuclear plant deal

Iran Says Deals to Rehabilitate, Develop Iraq Power Grid Finalized

READ MORE