TransCanada Corp. reported that refurbishing two units of the Bruce A nuclear plant near Kincardine has cost $3.8 billion to date.
The original cost estimate, when the project was announced in 2005 was $2.75 billion.
And the project is far from finished, as TransCanada says the plant wonÂ’t be restarted until the end of 2011, with commercial operation beginning in 2012.
It was originally planned to be restarted by the end of 2009.
TransCanada says its share of the total cost of the project is expected to be $2.4 billion. It owns Bruce Power in partnership with the OMERS pension fund and an employee group.
Related News
USDA Grants $4.37 Billion for Rural Energy Upgrades
TVA faces federal scrutiny over climate goals, electricity rates
Sen. Cortez Masto Leads Colleagues in Urging Congress to Support Clean Energy Industry in Economic Relief Packages
Substation Maintenance Training
Berlin Electric Utility Wins National Safety Award
The Haves and Have-Nots of Electricity in California
Sign Up for Electricity Forum’s Newsletter
Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.
Electricity Today T&D Magazine Subscribe for FREE
- Timely insights from industry experts
- Practical solutions T&D engineers
- Free access to every issue