China to upgrade Hunan power grid
From mid-January to mid-February of this year, the grid was greatly affected by the severe snowstorms that hit the country. The grid's transmission lines were encased in ice about 70 millimeters to 90 millimeters thick; the lines' designed limit was 15 millimeters to 20 millimeters.
The $340 million upgrade will cover six transmission lines with a total length of 531 kilometers and 38 crossovers at the 500-kilovolt (kV) level; 20 transmission lines with a total length of 733 kilometers and 38 crossovers at the 220 kV level; and 26 transmission lines with a total length of 452 kilometers and 165 crossovers at the 110 kV level.
Related departments of the SGC have been planning for various stages of the project, including tendering and construction. During construction, new technologies, new materials and new processes will be used. For instance, the application of multi-circuit, compact and narrow foundation steel pipe assembled towers will be adopted in 220 kV and 110 kV transmission lines.
Related News

Alberta breaks summer electricity record, still far short of capacity
CALGARY - Consumer use hit 10,638 MW, blowing past a previous high of 10,520 MW set on July 9, 2015, said the Alberta Electric System Operator (AESO).
“We hit a new summer peak and it’s likely we’ll hit higher peaks as the week progresses,” said AESO spokeswoman Tara De Weerd.
“We continue to have ample supply, our generators are very confident there aren’t any issues.”
That new peak was set at 4 p.m. but De Weerd said it was likely to be exceeded later in the day.
Heightened air conditioner use is normally a major driver of such peak electricity consumption, said De Weerd.
She…