Work on 132 MW combined cycle plant begins


NFPA 70b Training - Electrical Maintenance

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 12 hours Instructor-led
  • Group Training Available
Regular Price:
$699
Coupon Price:
$599
Reserve Your Seat Today

Ghana Thermal Power Expansion targets 5,000 MW with Takoradi upgrades, VRA gas turbines, hydro projects like Bui Dam, Canadian loan financing, improved transmission and distribution, and private investment to boost electricity generation and national electrification.

 

Essential Takeaways

Raise Ghana's generation to 5,000 MW by 2015 via Takoradi, hydro builds, grid upgrades, and private investment.

  • $185.36m Canadian-financed Takoradi expansion
  • Targeting 5,000 MW capacity with thermal and hydro
  • VRA adding gas turbines and heat-recovery steam units
  • Transmission and distribution modernized to cut losses

 

Vice President John Dramani Mahama cut the sod to begin work for an additional 132 megawatts combined cycle power plant at the Thermal Power Station at Aboadze near Takoradi.

 

The Vice President, who was assisted by Nana Kweku Binnah III, Omanhene of Shama Traditional Area Mahama, to perform the ceremony, said the contract for the project was estimated at (US) $185,359,651 and it was being financed with a loan from the Government of Canada and the Societe General of Canada and Investment Bank, as seen in Ontario power deals across the sector today.

He said the government wanted to improve thermal power supply from its present 2,000 megawatts to 5,000 megawatts by 2015, similar to Nigeria's 6,000 MW promise in the sub-region, to support the country's socio-economic development.

Vice President Mahama said government alone could not achieve this target with its own resources and would welcome private sector participation in the development of the country's electricity base to make energy available for domestic and industrial use.

He said the government has formulated a transparent framework within which private investors could operate and this was available at the Energy Commission.

Vice President Mahama said the government was considering means of correcting disparities in regional distribution of energy through the National Electrification Scheme.

He said the National Energy Accessibility Rate was 67 per cent and the Western Regional Energy Accessibility Rate, which was 50 per cent was below the national average.

Vice President Mahama said the government was endeavouring to improve the national rate and within the next three years, about 1,000 communities including communities in the Western Region would be provided with electricity.

He said government would construct hydro projects at various parts of the country in addition to the Bui Dam which was under construction to add 400 MW capacity to the existing power generation capacity.

Dr Kwabena Donkor, Deputy Minister of Energy, said the low electricity price regime based on reliable and cheap hydro-generation must be regarded as a thing of the past if the country was to improve on the availability, reliability and security of power supply amid ongoing power outages in Ghana that affect industrial and domestic use.

He said in the 1960s and 1970s, when power generation in the country was mainly from the Akosombo Dam, the country was able to produce and sell power for domestic and industrial use at very low prices.

Dr. Donkor said currently, there was a generation mix with about 50 per cent from thermal generation sources, using expensive crude oil and expensive diesel fuel with serious implications for cost of electricity generation and pricing, including power tariffs across the country.

He said: "The current generation mix throws up a production cost that is reflective of today's crude oil pricing that has hovered in the 80 United States dollars band for the last couple of months".

Dr. Donkor said the gravity of power sector generation challenge was exacerbated by the obsolescence of transmission and distribution infrastructure.

He said transformers and associated equipment manufactured and installed in the early 1950s still formed the backbone of transmission and distribution infrastructure.

Dr. Donkor said the nation under invested in the power sector after the 1960s, especially in transmission and distribution equipment and systems.

He said the transmission system was undergoing reinforcement to improve reliability and reduce vulnerability of the network, expand capacity network to support load growth and modernize the entire transmission network to meet internationally accepted standards of operation.

Dr. Donkor said the people have to collectively confront the high losses experienced in the distribution chain and while increased investment would reduce technical losses, the theft of power through illegal connections culminating in commercial losses must be addressed.

He called on security agencies, community groups and patriotic minded individuals to help to bring this under control by arresting and reporting the perpetuators who live in their communities.

Dr. Donkor said such commercial losses added to individual bills of consumers and it was, therefore, in their interest to help arrest this situation.

Mr. Kweku Andoh Awotwi, Chief Chief of the Volta River Authority (VRA), said the plant would consist of four gas turbines, four heat-recovery stream generator and two steam turbines.

He said the gas turbines would run on light crude oil, diesel oil and natural gas and the main contractor for the expansion project was the Canadian Commercial Corporation.

Mr Awotwi said the VRA remained committed to fulfilling its mandate of supplying electricity for socio-economic development in the country and the West Africa Sub-region.

He said the Takoradi Thermal Power Project, undertaken by the VRA, to supplement hydro sources of generation at Akosombo and Kpong, has contributed to achieving its corporate goal of ensuring efficient and reliable power supply.

Mr Derren Schemmer, Canadian High Commission in Ghana, said Ghana was the first country in the sub-region to benefit from his country's economic assistance.

He said many Canadian companies, including those highlighted in GVRD energy news coverage, wanted to do business in the country because of the government's good policies and good governance.

 

Related News

Related News

Christmas electricity spike equivalent to roasting 1.5 million turkeys: BC Hydro

BC Hydro Holiday Energy Saving Tips highlight electricity usage trends and power conservation during Christmas…
View more

Nuclear alert investigation won't be long and drawn out, minister says

Pickering Nuclear False Alert Investigation probes Ontario's emergency alert system after a provincewide cellphone, radio,…
View more

Cheap material converts heat to electricity

Polycrystalline Tin Selenide Thermoelectrics enable waste heat recovery with ZT 3.1, matching single crystals while…
View more

Demand for electricity in Yukon hits record high

Yukon Electricity Demand Record underscores peak load growth as winter cold snaps drive heating, lighting,…
View more

Why subsidies for electric cars are a bad idea for Canada

EV Subsidies in Canada influence greenhouse-gas emissions based on electricity grid mix; in Ontario and…
View more

Top Senate Democrat calls for permanent renewable energy, storage, EV tax credits

Clean Energy Tax Incentives could expand under Democratic proposals, including ITC, PTC, and EV tax…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.