Point Lepreau Cost Overruns strain New Brunswick as AECL's nuclear reactor refurbishment runs years late, driving $1M-per-day replacement power costs and spurring federal compensation talks amid election promises and contract obligations.

 

Essential Takeaways

Point Lepreau's delayed nuclear refurbishment raises costs and prompts federal compensation talks for New Brunswick.

  • AECL oversees refurbishment as Crown corporation
  • Project delayed about 3 years behind schedule
  • Replacement power costs about $1M per day
  • Ignatieff vows compensation talks with Premier Alward

 

The federal government has a responsibility to help cover some of the estimated $1 billion in cost overruns on the Point Lepreau refurbishment project, Liberal Leader Michael Ignatieff said.

 

In an interview with CBC News, Ignatieff said that New Brunswick should receive some compensation for the cost overruns associated with refurbishing Atlantic Canada's only nuclear reactor.

The upgrade of the nuclear reactor is three years behind schedule. It's costing about a million dollars a day for replacement power.

Conservative Leader Stephen Harper has repeatedly said that Atomic Energy of Canada Ltd., which is overseeing the refurbishment project, would honour its contractual obligations, but it would not pay any additional costs.

Ignatieff said if he's elected May 2, he would sit down with Premier David Alward to discuss possible compensation for the New Brunswick government.

"I know that a lot of New Brunswickers feel they are stuck with the Point Lepreau problem and it potentially adds millions and millions and millions of dollars to New Brunswickers' energy costs for households," Ignatieff said.

"This is not a problem the federal government can walk away from. AECL is a Crown corporation so we have some responsibility. I don't know all the details. I do know that I will sit with the premier when we get into office and say what do we do, how do we dig this one out together."

When pressed on how much Ignatieff thought the federal government should ante up to cover the cost overruns, the Liberal leader would not offer a specific figure.

Progressive Conservative MLAs voted in favour of the Liberal motion asking the federal government to cover all cost overruns at the project.

Energy Minister Craig Leonard said the government may have some leverage given the election campaign and ongoing nuclear plans discussions within the province.

"If there's an opportunity to enter into a dialogue with the federal government as a result of the election, we're certainly not going to pass that up. So as a result of the opposition motion, we felt we had to agree with it, as we would anyways, regardless of an election or not, because it simply says what we've been saying all along," said Leonard.

The reactor was supposed to be generating power again in September 2009. It is now expected Point Lepreau will not be running again until fall 2012.

The delays were caused when dozens of calandria tubes flunked air tightness tests after being fused with special inserts designed to hold them in place.

The calandria tubes — made to house smaller nuclear pressure tubes, which in turn contain radioactive nuclear fuel bundles — were the first major pieces of equipment to be installed in the reactor as part of Point Lepreau's much delayed refurbishment project. The tubes had to be taken out and then reinstalled.

 

Related News

Related News

Grounding and Bonding and The NEC - Section 250

Electrical Grounding and Bonding NEC 250 Training equips electricians with Article 250 expertise, OSHA compliance…
View more

The German economy used to be the envy of the world. What happened?

Germany's Economic Downturn reflects an energy crisis, deindustrialization risks, export weakness, and manufacturing stress, amid…
View more

Fire in manhole leaves thousands of Hydro-Québec customers without power

Montreal Power Outage linked to Hydro-Que9bec infrastructure after an underground explosion and manhole fire in…
View more

Judge: Texas Power Plants Exempt from Providing Electricity in Emergencies

Texas Blackout Liability Ruling clarifies appellate court findings in Houston, citing deregulated energy markets, ERCOT…
View more

Yukon receives funding for new wind turbines

Yukon Renewable Energy Funding backs wind turbines, grid-scale battery storage, and transmission line upgrades, cutting…
View more

Three Mile Island at center of energy debate: Let struggling nuclear plants close or save them

Three Mile Island Nuclear Debate spotlights subsidies, carbon pricing, wholesale power markets, grid reliability, and…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified