PMLD was developing the project with Community Energy Incorporated, which was acquired in 2006 by Iberdrola Renewables, a subsidiary of Grupo Iberdrola. However, Iberdrola withdrew from the project, deeming it too small and allowing PMLD to take control.
The city financed the $7.15 million project and selected Fuhrlander AG to provide two 1.5-megawatt FL-1500 wind turbine/generators. Lumus Construction Incorporated was selected to handle construction.
Civil site construction began in August 2007 off of Stage Coach Trail Access Road commenced. The turbines are expected to be delivered by Fuhrlander in April or May 2009. PMLD expects Lumus to complete construction and commissioning within 30 days of delivery. PLMD Manager Jonathan Fitch has said that the city might consider one or two more turbine/generator sites after this project is complete.
Related News
COVID-19 Pandemic Puts $35 Billion in Wind Energy Investments at Risk, Says Industry Group
Parisians vote to ban rental e-scooters from French capital by huge margin
Time running out for Ontario to formally request Pickering nuclear power station extension
ETP 2017 maps major transformations in energy technologies
How the U.S. Grid Is Adapting to Extreme Heat and Climate Stress
Ontario Extends Off-Peak Electricity Rates to Provide Relief for Families, Small Businesses and Farms
Sign Up for Electricity Forum’s Newsletter
Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.
Electricity Today T&D Magazine Subscribe for FREE
- Timely insights from industry experts
- Practical solutions T&D engineers
- Free access to every issue