PMLD was developing the project with Community Energy Incorporated, which was acquired in 2006 by Iberdrola Renewables, a subsidiary of Grupo Iberdrola. However, Iberdrola withdrew from the project, deeming it too small and allowing PMLD to take control.
The city financed the $7.15 million project and selected Fuhrlander AG to provide two 1.5-megawatt FL-1500 wind turbine/generators. Lumus Construction Incorporated was selected to handle construction.
Civil site construction began in August 2007 off of Stage Coach Trail Access Road commenced. The turbines are expected to be delivered by Fuhrlander in April or May 2009. PMLD expects Lumus to complete construction and commissioning within 30 days of delivery. PLMD Manager Jonathan Fitch has said that the city might consider one or two more turbine/generator sites after this project is complete.
Related News
CALIFORNIA: Why your electricity prices are soaring
New England Is Burning the Most Oil for Electricity Since 2018
UK Emergency energy plan not going ahead
Potent greenhouse gas declines in the US, confirming success of control efforts
Franklin Energy and Consumers Energy Support Small Businesses During COVID-19 with Virtual Energy Coaching
Electric vehicles are a hot topic in southern Alberta
Sign Up for Electricity Forum’s Newsletter
Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.
Electricity Today T&D Magazine Subscribe for FREE
- Timely insights from industry experts
- Practical solutions T&D engineers
- Free access to every issue