PMLD was developing the project with Community Energy Incorporated, which was acquired in 2006 by Iberdrola Renewables, a subsidiary of Grupo Iberdrola. However, Iberdrola withdrew from the project, deeming it too small and allowing PMLD to take control.
The city financed the $7.15 million project and selected Fuhrlander AG to provide two 1.5-megawatt FL-1500 wind turbine/generators. Lumus Construction Incorporated was selected to handle construction.
Civil site construction began in August 2007 off of Stage Coach Trail Access Road commenced. The turbines are expected to be delivered by Fuhrlander in April or May 2009. PMLD expects Lumus to complete construction and commissioning within 30 days of delivery. PLMD Manager Jonathan Fitch has said that the city might consider one or two more turbine/generator sites after this project is complete.
Related News
Hydro One CEO's $4.5M salary won't be reduced to help cut electricity costs
Analysis: Out in the cold: how Japan's electricity grid came close to blackouts
IAEA reactor simulators get more use during Covid-19 lockdown
Alberta sets new electricity usage record during deep freeze
Iran to Become Regional Hub for Renewable Energies
TransAlta Poised to Finalize Alberta Data Centre Agreement in 2025
Sign Up for Electricity Forum’s Newsletter
Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.
Electricity Today T&D Magazine Subscribe for FREE
- Timely insights from industry experts
- Practical solutions T&D engineers
- Free access to every issue