Site C dam could still be cancelled at '11th hour' if First Nations successful in court

VANCOUVER -
The Site C dam could still be stopped by an "eleventh hour" court ruling, according to the lawyer representing B.C. First Nations opposed to the massive hydroelectric project near Fort St. John.
The B.C. government, BC Hydro and West Moberly and Prophet River First Nations were in B.C. Supreme Court Feb. 28 to set a 120-day trial, expected to begin in March 2022.
That date means a ruling would come prior to the scheduled flooding of the dam's reservoir area in 2023 said Tim Thielmann, legal counsel for the West Moberly First Nation.
"The court has left itself the opportunity for an eleventh hour cancellation of the project," he said.
Construction continues
At the core of the case is First Nations arguments the multi-billion dollar BC Hydro dam will cause irreparable harm to its territory and way of life — rights protected under Treaty 8.
The West Moberly have previously warned it believes Site C constitutes a $1 billion treaty violation.
In 2018, the First Nations lost a bid for an injunction order, meaning construction of the dam is continuing.
First Nations 'deeply frustrated' after B.C. Supreme Court dismisses Site C injunction
The judge in the case said the ruling was made because if the First Nations lost the challenge, the project would be needlessly put into disarray.
Province, Nations enter talks to avoid litigation
Also this week the B.C. government announced it has entered into talks with BC Hydro and the two First Nations in an attempt to avoid the court process altogether.
Thielmann said the details of the talk are confidential, but his clients are willing to pursue all avenues in order to stop the dam from moving forward.
"They are trying to save what little is left [of the Peace River Valley]", he said.
Tim Thielmann of Sage Legal is representing the West Moberly First Nation in its lawsuit aimed at stopping Site C. (Sage Legal)
In the meantime, the parties will continue to prepare for the 2022 court dates.
The latest figure on the cost of the dam is $10.7 billion. When complete, it would power the equivalent of 450,000 homes a year.
Related News

OEB issues decision on Hydro One's first combined T&D rates application
TORONTO - The Ontario Energy Board (OEB) issued its Decision and Order on an application filed by Hydro One Networks Inc. (Hydro One) on August 5, 2021 seeking approval for changes to the rates it charges for electricity transmission and distribution, beginning January 1, 2023 and for each subsequent year through to December 31, 2027.
The proceeding resulted in the filing of a settlement proposal that the OEB has now approved after concluding that it is in the public interest.
The negotiated reductions in Hydro One's transmission and distribution revenue requirements over the 2023 to 2027 period total $482.7 million compared to…