EPCOR, Siemens strive for near-zero emission coal

By Canada News Wire


NFPA 70e Training

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 6 hours Instructor-led
  • Group Training Available
Regular Price:
$199
Coupon Price:
$149
Reserve Your Seat Today
A three-year initiative to design and engineer Canada's first near-zero emission thermal power plant reached a milestone today when EPCOR Utilities Inc. (EPCOR) selected Siemens Fuel Gasification Technology GmbH & Co. KG (Siemens) as the technology provider for the design of a coal gasification facility.

The selection is the latest step in the EPCOR-led Front End Engineering and Design (FEED) of an Integrated Gasification Combined Cycle (IGCC) technology power plant that could deliver improved air quality and capture carbon emissions for permanent storage.

Siemens will licence its SFG-500 coal gasifier technology to the FEED project. If subsequent investment and construction decisions go as planned, a 270-megawatt (net) generating station using the new technology would be targeted to commence operations in 2015.

"Today's agreement is a significant milestone in EPCOR's quest to take carbon capture and storage technologies from opportunity to operation," said EPCOR Senior Vice President, Dr. David Lewin. "This Genesee IGCC project alone has the potential to capture more than one and a quarter million tonnes of carbon dioxide emissions a year, which would make a significant contribution towards provincial and federal targets while providing a reliable source of baseload power generation."

Siemens has operated its gasification technologies for more than 20 years, using a wide variety of energy sources as feedstocks for the conversion process. In 2007, as part of the FEED study, 18 tonnes of coal from Genesee were shipped to Siemens Gasification Test Centre in Freiberg, Germany for performance testing.

"While we have secured a number of orders for our coal gasification technology in China, the U.S. and Australia, we are pleased to have our first order in Canada," said Michael Suess, CEO of the Fossil Power Generation Division of Siemens Energy. "This is the first time our gasifier technology will be used for a full-scale IGCC project. In the future IGCC power plants could make a significant contribution toward more reliable energy supply with maximized climate and environmental compatibility."

The Alberta Energy Research Institute, Natural Resources Canada and EPCOR have each contributed $11 million to the $33 million FEED project, which is located at EPCOR's Genesee Generating Station, 70 kilometres southwest of Edmonton, Alberta. The FEED project is being conducted in conjunction with the Canadian Clean Power Coalition, which is chaired by Dr. David Lewin.

In October 2007 the Genesee FEED study became the first project to be supported by the federal government's ecoENERGY Technology Initiative.

"Canada's fossil fuel resources are one of our country's biggest economic drivers, and our government is committed to developing cleaner ways to produce and use those resources," said the Honourable Gary Lunn, Minister of Natural Resources. "This project is an example of how our investments are advancing the technologies required to produce and use energy in ways that protect the health of both our environment and Canadians."

The FEED project is currently in its second phase, which is scheduled for completion in 2009. Following completion of the technology design work and financing decisions, EPCOR can enter into an agreement with Siemens to supply the gasification reactor and system components.

"This project is another demonstration of how government-industry partnerships are advancing Alberta's Climate Change Plan," said Doug Horner, Minister of Advanced Education and Technology. "Carbon capture and storage is an important strategy in reducing greenhouse gas emissions and this technology strengthens Alberta's position as a global leader in sustainable energy development."

EPCOR is preparing an Expression of Interest for the Genesee IGCC project, seeking to qualify under the Province of Alberta's $2 billion program for large-scale carbon capture and storage projects.

Related News

Chinese-built electricity poles plant inaugurated in South Sudan

Juba Power Distribution Expansion accelerates grid rehabilitation in South Sudan, adding concrete poles, medium and low voltage networks, and LED street lighting, funded by AfDB and executed by Power China for reliable, affordable electricity.

 

Key Points

A project to upgrade Juba's grid with concrete poles, MV-LV networks, and LED lighting for reliable, affordable power.

✅ 13,350 concrete poles produced locally for network rollout

✅ Medium and low voltage network rehabilitation and expansion

✅ LED street lighting and customer care improvements funded by AfDB

 

The South Sudan government has launched a factory producing concrete poles that will facilitate an ambitious project done by a Chinese company to rehabilitate and expand the Power Distribution System in Juba, its capital.

The Minister of Dams and Electricity, Dhieu Mathok, said that the factory, rented by Power China, will produce some 13,350 poles for the electricity distribution in the capital and other states.

"The main objective of this project is to increase the supply capacity and reliability of the power distribution system in Juba. Access to the grid will replace the use of generators by the population, allow supply of energy at more affordable price and, hence contribute toward economic growth and poverty eradication in South Sudan," Mathok said during the inauguration of the plant along the Yei road in Juba.

#google#

He disclosed that it will help solve the problem associated with non-availability of concrete poles for the project and to mitigate the risk of importing poles from other countries.

"This factory will create positive impact on the construction of the national grid in South Sudan. It is owned by South Sudanese business people but currently it has been taken over by Power China for a brief period of one year," he said.

South Sudan is largely generator driven economy with continued electricity blackout, and across the continent initiatives like Cape Town's municipal power build-out illustrate alternative approaches, in the wake of the collapse of the generator power plant operated by the South Sudan Electricity Corporation (SSEC) in 2013.

Wang Cun, an official with Power China said they got the contract to build the electricity project in June 2016 and that they will continue to support South Sudanese staff with skills and knowledge, drawing on advances such as PEM green hydrogen R&D that point to future low-carbon options, and also work with the government on several major power projects.

"We have achieved much from these projects and we also suffered much from the instability and continuous conflicts all these years, but we confirm and believe the year of 2018 will be a year of peace and development in South Sudan," Wang said, adding that the company has been operating in South Sudan since 2009.

He disclosed that Power China has conducted several projects before South Sudan won independence from Sudan in 2011 such as the peace road project from Renk to Malakal, Maridi water plant and Malakal municipal road projects.

Wang said they will immediately reorganize all necessary resources to increase post-production capacity and immediately shall commence the erection of these poles to all corners of Juba city and start the distribution.

"We shall do as we did before to recruit more local technicians, engineers and laborers during the construction period, so that they are there in place for similar projects in the near future. We shall make more efforts to improve these local staffs' working environment and to realize sustainable development of Power China and Sino-hydro in South Sudan," said Wang.

Power China has been committing itself in the economic development of South Sudan and has signed eight commercial contracts with the government of South Sudan since independence like the Juba-hydro power project and the Tharjiath thermal power plant project, while in China projects such as the Lawa hydropower station demonstrate ongoing hydropower expertise that can inform regional work.

Liu Xiaodong, the Charge d'Affaires at the Chinese embassy in South Sudan, said Power China has been working very hard in the engineering and procurement in the earlier stage of the project, and as China expands energy ties such as nuclear cooperation with Cambodia that demonstrate broader engagement, also thanked the South Sudan government and the African Development Bank for their strong support.

Liu added upon completion Juba will have an upgraded power distribution system with 2,250 lighting points along the main roads in the capital and lamps will be LED ones.

The project falls under the Juba Power Distribution System Rehabilitation and Expansion Project, which was funded by the African Development Bank (AfDB) and has undertaken an AfDB review of a Senegal power plant to inform regional energy decisions.

It comprises of five different lots like Rehabilitation of Diesel plant substation, Rehabilitation and Expansion of medium voltage network, low voltage network, and Rehabilitation and Expansion of street lighting and improvement of customer care.

 

Related News

View more

Electric Motor Testing Training

Electric Motor Testing Training covers on-line and off-line diagnostics, predictive maintenance, condition monitoring, failure analysis, and reliability practices to reduce downtime, optimize energy efficiency, and extend motor life in industrial facilities.

 

Key Points

An instructor-led course teaching on-line/off-line tests to diagnose failures, improve reliability, and cut downtime.

✅ On-line and off-line test methods and tools

✅ Failure modes, root cause analysis, and KPIs

✅ Predictive maintenance, condition monitoring, ROI

 

Our 12-Hour Electric Motor Testing Training live online instructor-led course introduces students to the basics of on-line and off-line motor testing techniques, with context from VFD drive training principles applicable to diagnostics.

September 10-11 , 2020 - 10:00 am - 4:30 pm ET

Our course teaches students the leading cause of motor failure. Electric motors fail. That is a certainty. And unexpectded motor failures cost a company hundreds of thousands of dollars. Learn the techniques and obtain valuable information to detect motor problems prior to failure, avoiding costly downtime, with awareness of lightning protection systems training that complements plant surge mitigation. This course focuses electric motor maintence professionals to achieve results from electrical motor testing that will optimize their plant and shop operations.

Our comprehensive Electric Motor Testing course emphasizes basic and advanced information about electric motor testing equipment and procedures, along with grounding practices per NEC 250 for safety and compliance. When completed, students will have the ability to learn electric motor testing techniques that results in increased electric motor reliability. This always leads to an increase in overall plant efficiency while at the same time decreasing costly motor repairs.

Students will also learn how to acquire motor test results that result in fact-based, proper motor maintenance management. Students will understand the reasons that electric motors fail, including grounding deficiencies highlighted in grounding guidelines for disaster prevention, and how to find problems quickly and return motors to service.

 

COURSE OBJECTIVE:

This course is designed to enable participants to:

  • Describe Various Equipment Used For Motor Testing And Maintenance.
  • Recognize The Cause And Source Of Electric Motor Problems, including storm-related hazards described in electrical safety tips for seasonal preparedness.
  • Explain How To Solve Existing And Potential Motor Problems, integrating substation maintenance practices to reduce upstream disruptions, Thereby Minimizing Equipment Disoperation And Process Downtime.
  • Analyze Types Of Motor Loads And Their Energy Efficiency Considerations, including insights relevant to hydroelectric projects in utility settings.

 

Complete Course Details Here

https://electricityforum.com/electrical-training/motor-testing-training

 

Related News

View more

Hydro One: No cut in peak hydro rates yet for self-isolating customers

Hydro One COVID-19 Rate Relief responds to time-of-use pricing, peak rates, and Ontario Energy Board rules as residents stay home, offering a Pandemic Relief Fund, flexible payments, and support for electricity bills amid off-peak adjustments.

 

Key Points

Hydro One's COVID-19 rate relief includes payment flexibility and hardship aid to ease time-of-use bill burdens.

✅ Advocates flexibility on time-of-use and peak rate impacts

✅ Pandemic Relief Fund offers aid and payment options

✅ OEB sets prices; utilities relay concerns and support

 

Hydro One says it is listening to requests by self-isolating residents for reduced kilowatt hour peak rates during the day when most people are home riding out the COVID-19 pandemic.

Peak rates of 20.8 cents per kw/h are twice as high from 7 a.m. to 7 p.m. – except weekends – than off-peak rates of 10.1 cents per kw/h and set by the Ontario Energy Board and not electricity providers such as Hydro One and Elexicon (formerly Veridian).

Frustrated electrical customers have signed their John Henry’s more than 50,000 times to a change.org petition demanding Hydro One temporarily slash rates for those already struggling with work closures and loss of income amid concerns about a potential recovery rate that could raise bills.

Alex Stewart, media relations spokesman for Hydro One, said the corporation is working toward a solution.

“While we are regulated to adhere to time-of-use pricing by the Ontario Energy Board, we’ve heard the concerns about time-of-use pricing and the idea of a fixed COVID-19 hydro rate as many of our customers will stay home to stop the spread of COVID-19,” Stewart told The Intelligencer.

“We continue to advocate for greater choice during this difficult time and are working with everyone in the electricity sector to ensure our customers are heard.”

Stewart said the electricity provider is reaching out to customers to help them during a difficult self-isolating and social distancing period in other ways to bring financial relief.

For example, new hardship measures are now in play by Hydro One to give customers some relief from ballooning electricity bills.

“This is a difficult time for everyone. Hydro One has launched a new Pandemic Relief Fund to support customers affected by the novel coronavirus COVID-19. As part of our commitment to customers, we will offer financial assistance, as well as increased payment flexibility, to customers experiencing hardship,” Stewart said.

“Hydro One is also extending its Winter Relief program to halt disconnections and reconnections to customers experiencing hardship during the coldest months of the year. This is about doing the right thing and offering flexibility to our customers so they have peace of mind and can concentrate on what matters most – keeping their loved ones safe.”

Stewart said customers having difficult times can visit the company’s website for more details at www.HydroOne.com/ReliefFund.

Elexicon Energy, meanwhile, said earlier the former Veridian company is passing along concerns to the OEB but otherwise can’t lower the rates unless directed to do so, as occurred when the province set off-peak pricing temporarily.

Chris Mace, Elexicon corporate communications spokesperson, said, “We don’t have the authority to do that.

“The Ontario Energy Board sets the energy prices. This is in the Ministry of Energy’s hands. We at Elexicon, along with other local distribution companies (LDC), have shared this feedback with the ministry and OEB to come up with some sort of solution or alternative. But this is out of our hands. We can’t shift anything.”

He suggested residents can shift the use of higher-drawing electrical appliances to early morning before 7 or in the evening after 7 p.m. when ultra-low overnight rates may apply.

Families may want to be “mindful whether it be cooking or laundry and so on and holding off on doing those until off-peak hours take effect. We are hearing customers and we have passed along those concerns to the ministry and the OEB.”

Hydro One power tips

Certain electrical uses in the home consumer more power than others, as reflected in Ontario’s electricity cost allocation approach:

62 per cent goes to space heating
19 per cent goes to water heaters
13 per cent goes to appliances
2 per cent goes to space cooling

 

Related News

View more

Closure of 3 Southern California power plants likely to be postponed

California Gas Plant Extensions keep Ormond Beach, AES Alamitos, and Huntington Beach on standby for grid reliability during heat waves, as regulators balance renewables, battery storage, and power, pending State Water Resources Control Board approval.

 

Key Points

State plan extending three coastal gas plants to 2026, adding capacity as California expands renewables and storage.

✅ Extends Ormond Beach, AES Alamitos, AES Huntington Beach

✅ Mitigates blackout risk during extreme heat and peak demand

✅ Pending State Water Resources Control Board approval

 

Temperatures in many California cities are cooling down this week, but a debate is simmering on how to generate enough electricity to power the state through extreme weather events while transitioning away from a reliance on fossil fuels as clean energy progress indicates statewide.

The California Energy Commission voted Wednesday to extend the life of three gas power plants along the state’s southern coast through 2026, even as natural-gas electricity records persist nationwide, postponing a shutoff deadline previously set for the end of this year. The vote would keep the decades-old facilities _ Ormond Beach Generating Station, AES Alamitos and AES Huntington Beach — open so they can run during emergencies.

The state is at a greater risk of blackouts during major events when many Californians simultaneously crank up their air conditioning, such as a blistering heat wave, illustrated by widespread utility shutoffs in recent years.

“We need to move faster in incorporating renewable energy. We need to move faster at incorporating battery storage. We need to build out chargers faster,” commissioner Patricia Monahan said amid an ongoing debate over the classification of nuclear power in California. “We’re working with all the energy institutions to do that, but we are not there yet.”

The plan, put together by the state’s Department of Water Resources, still needs final approval from the State Water Resources Control Board, which may vote on the issue next week. Democratic Gov. Gavin Newsom signed legislation last year creating an energy reserve the state could use as a last resort if there is likely to be an energy shortage, a challenge mirrored by Ontario electricity shortfall concerns elsewhere. The law allowed the Department of Water Resources to fund or secure power sources in those instances, after PG&E shutdown reasons drew attention to grid vulnerabilities.

The commission acknowledged it was a difficult decision. Environmentalists say the state needs to transition to more short- and long-term solutions that will help it move away from fossil fuels and to rely more on renewable energy sources like solar and wind, similar to Ontario's clean power push in recent years. They’re also concerned about the health impacts associated with pollution from gas plants.

 

Related News

View more

Energy Vault Secures $28M for California Green Hydrogen Microgrid

Calistoga Resiliency Centre Microgrid delivers grid resilience via green hydrogen and BESS, providing island-mode backup during PSPS events, wildfire risk, and outages, with black-start and grid-forming capabilities for reliable community power.

 

Key Points

A hybrid green hydrogen and BESS facility ensuring resilient, islanded power for Calistoga during PSPS and outages.

✅ 293 MWh capacity with 8.5 MW peak for critical backup

✅ Hybrid lithium-ion BESS plus green hydrogen fuel cells

✅ Island mode with black-start and grid-forming support

 

Energy Vault, a prominent energy storage and technology company known for its gravity storage, recently secured US$28 million in project financing for its innovative Calistoga Resiliency Centre (CRC) in California. This funding will enable the development of a microgrid powered by a unique combination of green hydrogen and battery energy storage systems (BESS), marking a significant step forward in enhancing grid resilience in the face of natural disasters such as wildfires.

Located in California's fire-prone regions, the CRC is designed to provide critical backup power during Public Safety Power Shutoff (PSPS) events—periods when utility companies proactively cut power to prevent wildfires. These events can leave communities without electricity for extended periods, making the need for reliable, independent power sources more urgent as many utilities see benefits in energy storage today. The CRC, with a capacity of 293 MWh and a peak output of 8.5 MW, will ensure that the Calistoga community maintains power even when the grid is disconnected.

The CRC features an integrated hybrid system that combines lithium-ion batteries and green hydrogen fuel cells, even as some grid-scale projects adopt vanadium flow batteries for long-duration needs. During a PSPS event or other grid outages, the system will operate in "island mode," using hydrogen to generate electricity. This setup not only guarantees power supply but also contributes to grid stability by supporting black-start and grid-forming functions. Energy Vault's proprietary B-VAULT DC battery technology complements the hydrogen fuel cells, enhancing the overall performance and resilience of the microgrid.

One of the key aspects of the CRC project is the utilization of green hydrogen. Unlike traditional hydrogen, which is often produced using fossil fuels, green hydrogen is generated through renewable energy sources like solar or wind power, with large-scale initiatives such as British Columbia hydrogen project accelerating supply, making it a cleaner and more sustainable alternative. This aligns with California’s ambitious clean energy goals and is expected to reduce the carbon footprint of the region’s energy infrastructure.

The CRC project also sets a precedent for future hybrid microgrid deployments across California and other wildfire-prone areas, with utilities like SDG&E Emerald Storage highlighting growing adoption. Energy Vault has positioned the CRC as a model for scalable, utility-scale microgrids that can be adapted to various locations facing similar challenges. Following the success of this project, Energy Vault is expanding its portfolio with additional projects in Texas, where it anticipates securing up to US$25 million in financing.

The funding for the CRC also includes the sale of an investment tax credit (ITC), a key component of the financing structure that helps make such ambitious projects financially viable. This structure is crucial as it allows companies to leverage government incentives to offset development costs, including CEC long-duration storage funding, thus encouraging further investment in green energy infrastructure.

Despite some skepticism regarding the transportation of hydrogen rather than producing it onsite, the project has garnered strong support. California’s Public Utilities Commission (CPUC) acknowledged the potential risks of transporting green hydrogen but emphasized that it is still preferable to using more harmful fuel sources. This recognition is important as it validates Energy Vault’s approach to using hydrogen as part of a broader strategy to transition to clean, reliable energy solutions.

Energy Vault's shift from its traditional gravity-based energy storage systems to battery energy storage systems, such as BESS in New York, reflects the company's adaptation to the growing demand for versatile, efficient energy solutions. The hybrid approach of combining BESS with green hydrogen represents an innovative way to address the challenges of energy storage, especially in regions vulnerable to natural disasters and power outages.

As the CRC nears mechanical completion and aims for full commercial operations by Q2 2025, it is poised to become a critical part of California’s grid resilience strategy. The microgrid's ability to function autonomously during emergencies will provide invaluable benefits not only to Calistoga but also to other communities that may face similar grid disruptions in the future.

Energy Vault’s US$28 million financing for the Calistoga Resiliency Centre marks a significant milestone in the development of hybrid microgrids that combine the power of green hydrogen and battery energy storage. This project exemplifies the future of energy resilience, showcasing a forward-thinking approach to mitigating the impact of natural disasters and ensuring a reliable, sustainable energy future for communities at risk. With its innovative use of renewable energy sources and cutting-edge technology, the CRC sets a strong example for future energy storage projects worldwide.

 

Related News

View more

New England takes key step to 1.2 GW of Quebec hydro as Maine approves transmission line

NECEC Clean Energy Connect advances with Maine DEP permits, Hydro-Québec contracts, and rigorous transmission line mitigation, including tapered vegetation, culvert upgrades, and forest conservation, delivering low-carbon power, broadband fiber, and projected ratepayer savings.

 

Key Points

A Maine transmission project delivering Hydro-Québec power with strict DEP mitigation, lower bills, and added broadband.

✅ DEP permits mandate tapered vegetation, culvert upgrades, land conservation

✅ Hydro-Québec to supply 9.55 TWh/yr via MA contracts; bill savings 2-4%

✅ Added broadband fiber in Somerset and Franklin; local tax benefits

 

The Maine DEP reviewed the Clean Energy Connect project for more than two years, while regional interest in cross-border transmission continued to grow, before issuing permits that included additional environmental mitigation elements.

"Collectively, the requirements of the permit require an unprecedented level of environmental protection and compensatory land conservation for the construction of a transmission line in the state of Maine," DEP said in a May 11 statement.

Requirements include limits on transmission corridor width, forest preservation, culvert replacement and vegetation management projects, while broader grid programs like vehicle-to-grid integration enhance clean energy utilization across the region.

"In our original proposal we worked hard to develop a project that provided robust mitigation measures to protect the environment," NECEC Transmission CEO Thorn Dickinson said in a statement. "And through this permitting process, we now have made an exceedingly good project even better for Maine."

NECEC will be built on land owned or controlled by Central Maine Power. The 53 miles of new corridor on working forest land will use a new clearing technique for tapered vegetation, while the remainder of the project follows existing power lines.

Environmentalists said they agreed with the decision, and the mitigation measures state regulators took, noting similar momentum behind new wind investments in other parts of Canada.

"Building new ways to deliver low-carbon energy to our region is a critical piece of tackling the climate crisis," CLF Senior Attorney Phelps Turner said in a statement. "DEP was absolutely right to impose significant environmental conditions on this project and ensure that it does not harm critical wildlife areas."

Once complete, Turner said the transmission line will allow the region "to retire dirty fossil fuel plants in the coming years, which is a win for our health and our climate."

The Massachusetts Department of Public Utilities in June 2019 advanced the project by approving contracts for the state's utilities to purchase 9,554,940 MWh annually from Hydro-Quebec. Officials said the project is expected to provide approximately 2% to 4% savings on monthly energy bills.

Total net benefits to Massachusetts ratepayers over the 20-year contract, including both direct and indirect benefits, are expected to be approximately $4 billion, according to the state's estimates.

NECEC "will also deliver significant economic benefits to Maine and the region, including lower electricity prices, increased local real estate taxes and reduced energy costs with examples like battery-backed community microgrids demonstrating local resilience, expanded fiber optic cable for broadband service in Somerset and Franklin counties and funding of economic development for Western Maine," project developers said in a statement.​

 

Related News

View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2025 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified