Areva wins Riel Station Switchyard contract

subscribe

ArevaÂ’s Transmission and Distribution (T&D) division in Canada has won an Engineering and Procurement contract to supply Manitoba Hydro with a 500/230 kV Air-insulated Switchyard at Riel Station east of Winnipeg.

The project forms part of Manitoba HydroÂ’s Riel Reliability Improvement Initiative, which aims to improve the reliability of electrical transmission to Winnipeg and Southern Manitoba.

Under the initiative, the new Riel Station will increase reliability by creating an alternate point at which electricity imported from the United States at 500 kV can be injected into southern ManitobaÂ’s 230 kV transmission system.

The 500 kV high-voltage transmission line, which currently operates between Dorsey Station northwest of Winnipeg, and Forbes Station in Minnesota, will be segmented at Riel to create a seamless link between Dorsey, Riel, and Forbes.

The station will also include equipment manufactured by Areva T&D, such as high-voltage circuit breakers, disconnect switches, instrument transformers, medium voltage switchgear, substation protection and control, and automation.

Michel Augonnet, Executive Vice President of Areva T&D’s Systems Business noted, “We’re very proud to continue our long term relationship with Manitoba Hydro, one of the largest energy utilities in Canada and Manitoba’s major utility, and to support them in their strong focus on reliable and efficient electrical transmission.”

Related News

manitoba transmission map

$453M Manitoba Hydro line to Minnesota could face delay after energy board recommendation

WINNIPEG - A recommendation from the National Energy Board could push back the construction start date of a $453-million hydroelectric transmission line from Manitoba to Minnesota.

In a letter to federal Natural Resources Minister Jim Carr, the regulatory agency recommends using a "certificate" approval process, which could take more time than the simpler "permit" process Manitoba Hydro favours.

The certificate process involves public hearings to weigh the merits of the project, which would then go to the federal cabinet for approval.

The NEB says this process would allow for more procedural flexibility and "address Aboriginal concerns that may arise in the circumstances of…

READ MORE
ford-cancels-wind

Doug Ford ‘proud’ of decision to tear up hundreds of green energy contracts

READ MORE

lake erie connector

The CIB and private sector partners to invest $1.7 billion in Lake Erie Connector

READ MORE

solar panel worker

Avista Commissions Largest Solar Array in Washington

READ MORE

hydro one logo

Hydro One, Avista to ask U.S. regulator to reconsider order against acquisition

READ MORE