Collider repairs at CERN to cost $25-million

subscribe

Fixing the world's largest atom smasher will cost at least 25 million Swiss francs ($25.8-million Cdn) and may take until early summer, its operator said.

An electrical failure shut down the Large Hadron Collider on September 19, nine days after the $10-billion machine started up with great fanfare.

The European Organization for Nuclear Research recently said that the repairs would be completed by May or early June. Spokesman James Gillies said the organization know as CERN is now estimating the restart will be at the end of June or later.

“If we can do it sooner, all well and good. But I think we can do it realistically (in) early summer,” he said.

The organization has attributed the shutdown to the failure of a single, badly soldered electrical connection.

The atom smasher operates at temperatures colder than outer space to get maximum efficiency, and experts needed to gradually warm the damaged section to better assess it, he said.

“Now the sector is warm, so they are able to go in and physically look at each of the interconnections,” Mr. Gillies told The Associated Press.

The cost of the work will fall within the organization's existing budget, he said.

The massive machine straddling the Swiss-French border was built to smash protons from hydrogen atoms together at high energy and record what particles are produced by the collisions, giving scientists a better idea of the makeup of the smallest components of matter.

That will show on a tiny scale what happened one-trillionth of a second after the so-called Big Bang, which many scientists theorize was the massive explosion that formed the universe. The theory holds that the universe was rapidly cooling at that stage and matter was changing rapidly.

Scientists have taken the setback in stride, saying that particle colliders always have such problems in the startup phase.

Related News

philippsburg-nuclear-power

Coronavirus impacts dismantling of Germany's Philippsburg nuclear plant

BERLIN - German energy company EnBW said the coronavirus outbreak has impacted plans to dismantle its Philippsburg nuclear power plant in Baden-Wurttemberg, southwest Germany.

The controlled detonation of Phillipsburg's cooling towers will now take place in mid-May at the earliest.

However, EnBW said the exact demolition date depends on many factors - including the further development in the coronavirus pandemic.

Philippsburg 2, a 1402MWe pressurised water reactor unit permanently shut down on 31 December 2019.

At the end of 2019, the Ministry of the Environment gave basic approval for decommissioning and dismantling of unit 2 of the Philippsburg nuclear power plant, inluding explosive demolition…

READ MORE
china high tech roads

Roads Need More Electricity: They Will Make It Themselves

READ MORE

siemens gamesa

Siemens Energy to unlock a new era of offshore green hydrogen production

READ MORE

Japan opens part of last town off-limits since nuclear leaks

READ MORE

europe at night

Six key trends that shaped Europe's electricity markets in 2020

READ MORE