No Electricity Means Extra Money For Albertans


NFPA 70b Training - Electrical Maintenance

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 12 hours Instructor-led
  • Group Training Available
Regular Price:
$699
Coupon Price:
$599
Reserve Your Seat Today
Industrial power consumers in Alberta will soon be getting paid to stop using electricity if called on by the provincial grid operator.

The notion isnÂ’t as twisted as it seems: the thousands of megawatts continuously cruising the provinceÂ’s web of transmission lines are kept in near-perfect harmony with demand loads to ensure the grid remains stable.

But a lightning strike at the intertie between Alberta and B.C., the provinceÂ’s main source of imported power, could throw off the balance between supply and demand if industry continues to suck power from the grid.

Hence the new Line Load Shed Service — Imports LSSi announced Wednesday by the Alberta Electric System Operator.

The contracted project ensures six large power consumers in the province will immediately trim back their demand if there is a sudden drop in imports, said Kris Aksomitis, AESO manager for demand response.

“This allows us to more fully utilize existing physical infrastructure,” Aksomitis said.

The intertie with B.C. has a capacity of 1,200 megawatts for imports, but currently Alberta is limited importing 600 MW. The program would allow another 100 to 200 MW of power to flow in case of an emergency, say a lightning strike on the border, he said.

“It balances off that instantaneous shortage by tripping loads, so it rebalances the system near instantaneously,” he said.

The program is triggered when imports exceed 400 to 500 MW, at which point the participants are alerted to switch on specialized monitors. If frequency on the grid drops to 59.5 hertz from the normal 60 Hz. the monitors immediately trim power demand.

“It allows us to import more because we can maintain stability after an event due to this service,” Aksomitis said. “Without this service we would have to limit how much we could import on the basis that if that supply disappeared we still have to maintain reliability.”

The AESO selected 432 MW of load capacity for the program from Alberta Newsprint Company Ranger Board, a division of West Fraser Mills EnerNOC Ltd. ERCO Worldwide, A Division of Superior Plus LP Millar Western Forest Products Ltd. and Slave Lake Pulp Partnership.

Contract vary from one to three years. Terms were not released.

Industrial use represents 60 per cent of the power demand in Alberta, different from most other jurisdictions in Canada where residential use drives electricity loads.

Related News

Lawmakers push bill to connect Texas grid to rest of the nation

Connect the Grid Act links ERCOT to neighboring grids via high-voltage interconnections, enhancing reliability, resilience,…
View more

Ontario to seek new wind, solar power to help ease coming electricity supply crunch

Ontario Clean Grid Plan outlines emissions-free electricity growth, renewable energy procurement, nuclear expansion at Bruce…
View more

Alberta's Rising Electricity Prices

Alberta Last-Resort Power Rate Reform outlines consumer protection against market volatility, price spikes, and wholesale…
View more

Electrifying Manitoba: How hydro power 'absolutely revolutionized' the province

Manitoba Electrification History charts arc lights, hydroelectric dams, Winnipeg utilities, transmission lines, rural electrification, and…
View more

U.S. Electricity Sales Projections Continue to Fall

US Electricity Demand Outlook examines EIA forecasts, GDP decoupling, energy efficiency, electrification, electric vehicles, grid…
View more

Global electric power demand surges above pre-pandemic levels

Global Power Sector CO2 Surge 2021 shows electricity demand outpacing renewable energy, with coal and…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.