Site preparation begins for Finnish cogeneration plant

subscribe

Westenergy Oy recently began site preparation for a 13-megawatt (MW) cogeneration plant to be situated 10 kilometres from the Finnish municipality of Vaasa in western Finland.

Von Roll Inova, the Swiss subsidiary of Austrian Energy & Environment, was awarded a 60 million euro (US $90 million) contract for the engineering, design and supply of the main boiler, process technology, combustion and steam generation systems, including support and ancillary systems for the power facility.

The contract for the supply of the turbine and generator has not been finalized yet, and a contract is expected to be awarded in the coming months, project managers told Industrial Info.

The highly efficient plant concept is based on Von Roll Inova's proven combustion technology. The onsite 13-MW turbine will generate enough electricity to serve more than 30,000 households. The plant will process 150,000 tonnes of domestic and commercial waste per year from about 60 municipalities in western Finland in an environmentally friendly manner. The plant will also generate 40 MW of district heat.

Site preparation began at the beginning of November, and the plant's structural erection is expected to start in the first months of 2010. The plant is projected to begin supplying district heating in 2013.

Von Roll Inova is a world leader in energy-from-waste technology. Headquartered in Zurich, Von Roll Inova has branches in France, Japan, Sweden, Switzerland, China and the United States.

Related News

nuclear

First Nuclear Reactors Built in 30 Years Take Shape at Georgia Power Plant

GEORGIA - Construction is ongoing for two new nuclear reactors, Units 3 and 4, at Georgia Power's Alvin W. Vogtle Electric Generating Plant in Waynesboro, Ga. the first new nuclear reactors to be constructed in the United Stated in 30 years that will provide electricity to more than 500,000 homes and businesses once operational.

Construction on Unit 3 started in March 2013 with an expected completion date of November 2021. For Unit 4, work began in November 2013 with a targeted delivery date of November 2022. Each unit houses a Westinghouse AP1000 (Advanced Passive) nuclear reactor that can generate about 1,117…

READ MORE
us electricity generation graph 2021

Annual U.S. coal-fired electricity generation will increase for the first time since 2014

READ MORE

power lines

Energy prices trigger EU inflation, poor worst hit

READ MORE

taiwan power outage

Taiwan's economic minister resigns over widespread power outage

READ MORE

enmax

Electricity bills on the rise in Calgary after

READ MORE