Siemens secures contract for HVDC link


NFPA 70E Training

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 6 hours Instructor-led
  • Group Training Available
Regular Price:
$199
Coupon Price:
$149
Reserve Your Seat Today

New Zealand Pole 3 HVDC link connects North and South Islands via thyristor valves, Siemens converter stations, 220 kV switchyards, and undersea cables, boosting grid reliability, capacity to 1,000-1,200 MW, and integrating hydropower and renewables.

 

Breaking Down the Details

An HVDC upgrade replacing Pole 1 to lift inter-island capacity to 1,000-1,200 MW and enhance AC-DC grid reliability.

  • Replaces aging Pole 1 with thyristor valve technology
  • Siemens to build converter stations at Benmore and Haywards
  • 220 kV switchyards augmented; new voltage support at Haywards

 

National electricity grid operator Transpower New Zealand Limited has awarded the principal contract for construction of the Pole 3 High Voltage Direct Current (HVDC) link to Siemens AG.

 

Last September, the government approved the $490 million inter-island electricity link, which will connect the North and South Islands of New Zealand.

The Pole 3 project will replace the existing Pole 1 equipment at substations on both sides of the link, at Haywards, north of Wellington, and at Benmore on South Island. The equipment will be replaced with thyristor valve connectors and units as part of broader smart grid work underway in New Zealand.

Under the contract, Siemens will build converter stations on each side of the link, augment 220-kilovolt (kV) switchyards at both substations, and construct a new voltage support system at Haywards to enhance grid reliability across New Zealand. Officials have indicated that Pole 3 will begin functioning by 2012 and that Pole 1 will be gradually decommissioned. The project is estimated to increase the capacity of the link to 1,000 MW by 2012 and to 1,200 MW by 2014.

State-owned Transpower operates the 12,000-kilometer national grid network, connecting 170 substations. The existing link, which was commissioned in 1965, transmits power from South Island to North Island. Electricity is converted from alternating current (AC) to direct current (DC) at Benmore in Waitaki Valley, and transmitted to Cooks Strait. At this point, undersea cables, similar to subsea renewable links in the UK, carry power to the Haywards substation on North Island. At Haywards in Hutt Valley, electricity is converted from DC to AC and linked to the national grid.

The Pole 3 project is considered to be critical to provide balanced use of power between the islands and allow seamless transmission of electricity. Civil and seismic strengthening activities have commenced onsite, while parallel smart grid pilots abroad inform implementation. Siemens is expected to begin construction by March 2010.

The recently published electricity sector review, commissioned by the New Zealand government, indicates that it has become critical to develop competitiveness in the national energy sector. The study says that competition will assist in bringing down the spiraling price of electricity in New Zealand. New Zealand's energy mix is dominated by hydropower, which accounts for 60% of the power generated and mirrors large hydropower transmission efforts abroad. Thermal power and energy from renewable sources (such as geothermal and wind) contribute 30% and 10%, respectively, to the national grid.

The country has experienced at least three dry years in the past 10 years, which led to a slump in power generation and a subsequent hike in power prices, highlighting the value of cross-border transmission options for resilience.

The domestic electricity market is dominated by three state-controlled companies: Mighty River Power Limited, Genesis Power Limited, and Meridian Energy Limited. Prominent private sector players include TrustPower and Contact Energy. Power companies in New Zealand reportedly gained about $2.9 billion due to high prices during a six-year period until mid-2007, especially during dry years.

The construction and operation of Pole 3 is expected to improve power contribution to the peak demand in North Island. The project also may assist in deferring new power plant construction. The advanced technology to be used in the Pole 3 project is expected to offer greater flexibility in power generation and transmission, and reduce distribution losses across the grid. The link will ensure greater reliability between the islands, as it will mitigate problems if Pole 2 fails, and will spur the development of renewable sources of energy.

Related News

Almost 500-mile-long lightning bolt crossed three US states

Longest Lightning Flash Record confirmed by WMO: a 477.2-mile megaflash spanning Mississippi, Louisiana, and Texas,…
View more

Romania moves to terminate talks with Chinese partner in nuke project

Romania Ends CGN Cernavoda Nuclear Deal, as Nuclearelectrica moves to terminate negotiations on reactors 3…
View more

Ontario's electricity operator kept quiet about phantom demand that cost customers millions

IESO Fictitious Demand Error inflated HOEP in the Ontario electricity market, after embedded generation was…
View more

Brazilian electricity workers call for 72-hour strike

Eletrobras Privatization Strike sparks a 72-hour CNE walkout by Brazil's electricity workers, opposing asset sell-offs…
View more

Turkish powership to generate electricity from LNG in Senegal

Karpowership LNG powership in Senegal will supply 15% of the grid, a 235 MW floating…
View more

Ukraine Leans on Imports to Keep the Lights On

Ukraine Electricity Imports surge to record levels as EU neighbors bolster grid stability amid Russian…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.