West Virginia approval sought for multi-state power line
Developers of the Potomac-Appalachian Transmission Highline, or PATH, said they planned to file similar requests with regulatory agencies in Maryland and Virginia in the next 10 days.
Columbus, Ohio-based American Electric Power and Greensburg, Pa.-based Allegheny Energy have said the 765-kilovolt line is needed to address regional electrical reliability concerns. The utilities originally planned to have the line operational by 2013, but agreed to delay it a year based an analysis by regional grid operator PJM Interconnection.
PJM's analysis said the project wasn't needed until 2014.
The filing starts a 400-day clock for the PSC's review and decision, said agency spokeswoman Sarah Robertson. The agency is expected to hold public hearings while reviewing the application.
The filing comes as Eastern Panhandle residents planned a May 31 protest. Keryn Newman and Patience Wait planned to take advantage of routine traffic jams on U.S. 340 to protest the line's proposed route through Jefferson County. The highway is often congested by weekend motorists traveling to fish or canoe on the Potomac River or visit Harpers Ferry National Historical Park.
As envisioned, PATH would travel from AEP's John Amos power plant in western West Virginia to a substation in Frederick, Md. The line would cross central West Virginia before passing through Clarke, Frederick and Loudoun counties in Virginia. The line then crosses back into West Virginia before ending in Maryland.
"We understand the concerns about the impact of transmission lines and will work with the states and landowners to address concerns," Michael Morris, AEP's chairman, president and chief executive, said in a prepared statement.
The West Virginia Highlands Conservancy said the transmission line would promote the use of coal as an energy source, ruin scenic vistas and increase utility rates for customers.
Last month, the state Supreme Court rejected similar arguments when it decided not to interfere with a separate high-voltage line Allegheny Energy proposes to build through northern West Virginia.
Related News

Expanding EV Charging Infrastructure in Calgary's Apartments and Condos
CALGARY - As the demand for electric vehicles (EVs) continues to rise, Calgary is taking significant strides to enhance its charging infrastructure, particularly in apartment and condominium complexes. A recent initiative has been introduced to facilitate the installation of EV charging stations in these residential buildings, addressing a critical barrier for potential EV owners living in multi-unit dwellings.
The Growing EV Market
Electric vehicles are no longer a niche market; they have become a mainstream option for many consumers. As of late 2023, EV sales have surged, with projections indicating that the trend will only continue. However, a significant challenge…