West Virginia approval sought for multi-state power line

subscribe

The developers of a multi-state power line asked for state Public Service Commission's approval to build the 280-mile line between West Virginia and Maryland.

Developers of the Potomac-Appalachian Transmission Highline, or PATH, said they planned to file similar requests with regulatory agencies in Maryland and Virginia in the next 10 days.

Columbus, Ohio-based American Electric Power and Greensburg, Pa.-based Allegheny Energy have said the 765-kilovolt line is needed to address regional electrical reliability concerns. The utilities originally planned to have the line operational by 2013, but agreed to delay it a year based an analysis by regional grid operator PJM Interconnection.

PJM's analysis said the project wasn't needed until 2014.

The filing starts a 400-day clock for the PSC's review and decision, said agency spokeswoman Sarah Robertson. The agency is expected to hold public hearings while reviewing the application.

The filing comes as Eastern Panhandle residents planned a May 31 protest. Keryn Newman and Patience Wait planned to take advantage of routine traffic jams on U.S. 340 to protest the line's proposed route through Jefferson County. The highway is often congested by weekend motorists traveling to fish or canoe on the Potomac River or visit Harpers Ferry National Historical Park.

As envisioned, PATH would travel from AEP's John Amos power plant in western West Virginia to a substation in Frederick, Md. The line would cross central West Virginia before passing through Clarke, Frederick and Loudoun counties in Virginia. The line then crosses back into West Virginia before ending in Maryland.

"We understand the concerns about the impact of transmission lines and will work with the states and landowners to address concerns," Michael Morris, AEP's chairman, president and chief executive, said in a prepared statement.

The West Virginia Highlands Conservancy said the transmission line would promote the use of coal as an energy source, ruin scenic vistas and increase utility rates for customers.

Last month, the state Supreme Court rejected similar arguments when it decided not to interfere with a separate high-voltage line Allegheny Energy proposes to build through northern West Virginia.

Related News

lake erie connector

The CIB and private sector partners to invest $1.7 billion in Lake Erie Connector

TORONTO - The Canada Infrastructure Bank (CIB) and ITC Investment Holdings (ITC) have signed an agreement in principle to invest $1.7 billion in the Lake Erie Connector project.

Under the terms of the agreement, the CIB will invest up to $655 million or up to 40% of the project cost. ITC, a subsidiary of Fortis Inc., and private sector lenders will invest up to $1.05 billion, the balance of the project's capital cost.

The CIB and ITC Investment Holdings signed an agreement in principle to invest $1.7B in the Lake Erie Connector project.

The Lake Erie Connector is a proposed 117 kilometre underwater…

READ MORE
Substation Maintenance Training

Substation Maintenance Training

READ MORE

first-reacto-installed-at-the-uk-latest-nuclear-power-station

First Reactor Installed at the UK’s Latest Nuclear Power Station

READ MORE

ns rate increase

Nova Scotia Premier calls on regulators to reject 14% electricity rate hike agreement

READ MORE

montana solar

Basin Electric and Clenera Renewable Energy Announce Power Purchase Agreement for Montana Solar Project

READ MORE