First ultra-supercritical unit goes online

The first 1,000-megawatt MW ultra-supercritical unit in central China's Anhui province was successfully connected to the grid recently. This paves a firm foundation for the load test and 68-hour full-load trial operation in the next stage.

Wenergy Tongling Power Plant's Phase VI Expansion Project is a key project for electric power development in the Anhui province. The project has a total planned capacity of two 1,000-MW ultra-supercritical coal-fired units.

Wenergy Tongling Power Generation Company Limited, a joint venture of Anhui Wenergy Company Limited, which is the listed flagship of Anhui Wenergy Group, and Huainan Mining Group Company Limited, is responsible for the construction and operation of the project. China Power Engineering Consulting Group Corporation served as the engineering, procurement and construction EPC firm for the project. Anhui No. 2 Electric Power Engineering and Construction Company is responsible for the construction and installation of the unit.

According to the nation's policy of replacing smaller, less efficient units with larger ones, the new unit will replace two 125-MW units built in Phase III of the Tongling Power Plant's construction. These two units kicked off construction in November 1987 and were commissioned in 1989 and 1990, respectively.

Prior to the final approval of the Phase VI Expansion, these two units had been shutdown since October 2007. After the commissioning of Unit 5, the two units were dismantled on April 2, 2011. According to the schedule, the new unit will begin commercial operation by the end of this month.

Related News

uk-energy-transition-stalled-by-supply-delays

UK's Energy Transition Stalled by Supply Delays

LONDON - The United Kingdom's ambitious plans to transition to clean energy are encountering significant obstacles due to prolonged delays in obtaining essential equipment such as transformers and other electrical components. These supply chain challenges are impeding the nation's progress toward decarbonizing its power sector by 2030.

Supply Chain Challenges

The global surge in demand for renewable energy infrastructure has led to extended lead times for critical components. For example, Statera Energy's storage plant in Thurrock experienced a 16-month delay for transformers from Siemens Energy. Such delays threaten the UK's goal to decarbonize power supplies by 2030.

Economic Implications

These…

READ MORE
kiev electricity

More Managers Charged For Price Fixing At Ukraine Power Producer

READ MORE

powerlines

More red ink at Manitoba Hydro as need for new power generation looms

READ MORE

phone pad

Shocking scam: fraudster pretending to be from BC Hydro attempts to extort business

READ MORE

global power demand chart

Global electric power demand surges above pre-pandemic levels

READ MORE