Lithuania eyes Areva, Candu, GE, Westinghouse for new nuclear
"They all are working with us. Which one is chosen will depend on the quality of the proposal - the best price and conditions," Saulius Specius, a LEO LT board member, told reporters in Vilnius.
"We will try to speed up the construction of the plant so that the first unit is ready in 2016," he added.
Initial plans had called for the new facility to come on-stream between 2018- 21 at a cost of 14 billion litas ($5.87 billion dollars.)
"The maximum capacity of the plant remains at 3,400 (megawatts) - statements that its capacity has been reduced to 2,200 megawatts are not true," LEO LT chairman Rymantas Juozaitis said following reports last week that the organization planned to scale back capacity.
"Output shares in megawatts to be assigned or chosen by the partners will be decided in the future. We know two things - Lithuania will have the share of 1, 300 megawatts and at least 34 per cent of the new facility management company," Specius added.
Lithuania's neighbors Poland, Latvia and Estonia are expected be LEO's partners in the new facility, to be known as the Visaginas Nuclear Power Plant.
With a population of some 38 million Poland is far larger than its Baltic partners, all with populations under 4 million, and has demanded a 1,000-1,200 megawatts share of the new plant's output.
Latvia and Estonia have previously requested shares of 400-500 megawatts each.
The Lithuanian Electricity Organization is a majority state-owned (61.7%) energy holding company with the remaining shares held by the privately-owned NDX Energija.
Lithuania needs the new nuclear facility to fill the power gap that will emerge when its Soviet-era Iganlina plant closes in 2010 in accordance with terms Lithuania agreed with the European Commission for its 2004 entry to the European Union.
Related News

Tucson Electric Power plans to end use of coal-generated electricity by 2032
TUCSON - In a dramatic policy shift, Tucson Electric Power says it will stop using coal to generate electricity by 2032 and will increase renewable energy's share of its energy load to more than 70% by 2035.
As part of that change, the utility will stop buying electricity from its two units at its coal-fired Springerville Generating Station by 2032. The plant, TEP's biggest power source, provides about 35% of its energy.
The utility already had planned to start up two New Mexico wind farms and a solar storage plant in the Tucson area by next year. The new plan calls for…