Removing radioactive tubes causes delay at Point Lepreau


NFPA 70E Training

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 6 hours Instructor-led
  • Group Training Available
Regular Price:
$199
Coupon Price:
$149
Reserve Your Seat Today
The delicate task of removing highly radioactive pressure tubes from the nuclear reactor at the Point Lepreau power station west of Saint John is causing a further delay in refurbishing the plant, according to NB Power.

The 380 tubes have to be removed by a special tool, and then crushed into small pieces for handling and storage, the corporation explained.

"One of the challenges we are facing is that pieces of the crushed pressure tubes are being caught inside the automated tooling, resulting in additional downtime for equipment maintenance and repairs," the report said.

"Effective planning for tooling maintenance and radiation work is imperative to the safety of our workers, as the pressure tubes are the most radioactive components to be removed from the reactor," the report said.

"While the project work has been further delayed, we are carefully reviewing the upcoming work sequences to identify opportunities to recover time on our schedule."

The Point Lepreau Nuclear Generating Station is the only nuclear power plant in the Atlantic provinces. It has been shut down for a major refit since April 2008. At full operation, the 25-year-old plant produces 30 per cent of the power the province uses.

NB Power says this is the first refurbishment of a CANDU 6 reactor in the world, and will extend the life of the power station for 25 to 30 years.

The work has been contracted out to Atomic Energy of Canada Ltd., but NB Power has loaned AECL some of its senior staff to help speed things up.

NB Power says it has warned AECL, a nuclear technology provider with contracts around the world, that it faces both financial penalties and damage to its reputation if the Point Lepreau work continues to stretch beyond the length of time promised when the refurbishment contract was signed.

Related News

New Jersey, New York suspending utility shut-offs amid coronavirus pandemic

NY & NJ Utility Shutoff Moratorium suspends power, heat, and water disconnections amid COVID-19, as…
View more

Ontario explores possibility of new, large scale nuclear plants

Ontario Nuclear Expansion aims to meet rising electricity demand and decarbonization goals, complementing renewables with…
View more

Multi-billion-dollar hydro generation project proposed for Meaford military base

Meaford Pumped Storage Project aims to balance the grid with hydro-electric generation, a hilltop reservoir,…
View more

Opinion: Nuclear Beyond Electricity

Nuclear decarbonization leverages low-carbon electricity, process heat, and hydrogen from advanced reactors and SMRs to…
View more

Opinion: UK Natural Gas, Rising Prices and Electricity

European Energy Market Crisis drives record natural gas and electricity prices across the EU, as…
View more

Thermal power plants’ PLF up on rising demand, lower hydro generation

India Coal Power PLF rose as capacity utilisation improved on rising peak demand and hydropower…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.