Removing radioactive tubes causes delay at Point Lepreau


Protective Relay Training - Basic

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 12 hours Instructor-led
  • Group Training Available
Regular Price:
$699
Coupon Price:
$599
Reserve Your Seat Today
The delicate task of removing highly radioactive pressure tubes from the nuclear reactor at the Point Lepreau power station west of Saint John is causing a further delay in refurbishing the plant, according to NB Power.

The 380 tubes have to be removed by a special tool, and then crushed into small pieces for handling and storage, the corporation explained.

"One of the challenges we are facing is that pieces of the crushed pressure tubes are being caught inside the automated tooling, resulting in additional downtime for equipment maintenance and repairs," the report said.

"Effective planning for tooling maintenance and radiation work is imperative to the safety of our workers, as the pressure tubes are the most radioactive components to be removed from the reactor," the report said.

"While the project work has been further delayed, we are carefully reviewing the upcoming work sequences to identify opportunities to recover time on our schedule."

The Point Lepreau Nuclear Generating Station is the only nuclear power plant in the Atlantic provinces. It has been shut down for a major refit since April 2008. At full operation, the 25-year-old plant produces 30 per cent of the power the province uses.

NB Power says this is the first refurbishment of a CANDU 6 reactor in the world, and will extend the life of the power station for 25 to 30 years.

The work has been contracted out to Atomic Energy of Canada Ltd., but NB Power has loaned AECL some of its senior staff to help speed things up.

NB Power says it has warned AECL, a nuclear technology provider with contracts around the world, that it faces both financial penalties and damage to its reputation if the Point Lepreau work continues to stretch beyond the length of time promised when the refurbishment contract was signed.

Related News

Enbridge Insists Storage Hub Lives On After Capital Power Pullout

Enbridge Alberta CCS Project targets carbon capture and storage in Alberta, capturing emissions from industrial…
View more

Brazilian electricity workers call for 72-hour strike

Eletrobras Privatization Strike sparks a 72-hour CNE walkout by Brazil's electricity workers, opposing asset sell-offs…
View more

What's at stake if Davis-Besse and other nuclear plants close early?

FirstEnergy Nuclear Plant Closures threaten Ohio and Pennsylvania jobs, tax revenue, and grid stability, as…
View more

National Grid expands dynamic line ratings to unlock existing overhead T&D capacity

Dynamic Line Rating Rollout increases real-time transmission capacity on overhead lines with grid-enhancing sensors and…
View more

Cost of US nuclear generation at ten-year low

US Nuclear Generating Costs 2017 show USD33.50/MWh for nuclear energy, the lowest since 2008, as…
View more

B.C. Commercial electricity consumption plummets during COVID-19 pandemic

BC Hydro COVID-19 Relief Fund enables small businesses to waive electricity bills for commercial properties…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified