Removing radioactive tubes causes delay at Point Lepreau


Substation Protection Training - Protect Transformers, Buses and Lines

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 12 hours Instructor-led
  • Group Training Available
Regular Price:
$799
Coupon Price:
$699
Reserve Your Seat Today
The delicate task of removing highly radioactive pressure tubes from the nuclear reactor at the Point Lepreau power station west of Saint John is causing a further delay in refurbishing the plant, according to NB Power.

The 380 tubes have to be removed by a special tool, and then crushed into small pieces for handling and storage, the corporation explained.

"One of the challenges we are facing is that pieces of the crushed pressure tubes are being caught inside the automated tooling, resulting in additional downtime for equipment maintenance and repairs," the report said.

"Effective planning for tooling maintenance and radiation work is imperative to the safety of our workers, as the pressure tubes are the most radioactive components to be removed from the reactor," the report said.

"While the project work has been further delayed, we are carefully reviewing the upcoming work sequences to identify opportunities to recover time on our schedule."

The Point Lepreau Nuclear Generating Station is the only nuclear power plant in the Atlantic provinces. It has been shut down for a major refit since April 2008. At full operation, the 25-year-old plant produces 30 per cent of the power the province uses.

NB Power says this is the first refurbishment of a CANDU 6 reactor in the world, and will extend the life of the power station for 25 to 30 years.

The work has been contracted out to Atomic Energy of Canada Ltd., but NB Power has loaned AECL some of its senior staff to help speed things up.

NB Power says it has warned AECL, a nuclear technology provider with contracts around the world, that it faces both financial penalties and damage to its reputation if the Point Lepreau work continues to stretch beyond the length of time promised when the refurbishment contract was signed.

Related News

Mercury in $3 billion takeover bid for Tilt Renewables

Mercury Energy Tilt Renewables acquisition signals a trans-Tasman energy push as PowAR and Mercury split…
View more

As Maine debates 145-mile electric line, energy giant with billions at stake is absent

Hydro-Quebec NECEC Transmission Line faces Maine PUC scrutiny over clean energy claims, greenhouse gas emissions,…
View more

EU opens consultation on Dutch electricity market reforms to tackle shortages

Dutch electricity market consultation invites stakeholder input on EU reforms, supply security, and market design.…
View more

Ontario introduces new 'ultra-low' overnight hydro pricing

Ontario Ultra-Low Overnight Electricity Rates cut costs for shift workers and EV charging, with time-of-use…
View more

New Mexico Could Reap $30 Billion Driving on Electricity

New Mexico EV Benefits highlight cheaper fuel, lower maintenance, cleaner air, and smarter charging, cutting…
View more

B.C. Hydro misled regulator: report

BC Hydro SAP Oversight Report assesses B.C. Utilities Commission findings on misleading testimony, governance failures,…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified