TransAlta adds new wind in Gaspe

subscribe

TransAlta Corp, Canada's biggest publicly owned electricity producer, expanded its wind portfolio in Quebec by adding a $205 million wind project.

The 66 megawatt MW New Richmond wind project, which is expected to start operating commercially in the fourth quarter of 2012, will be located on the Gaspe Peninsula.

"The addition of the New Richmond project will increase our wind portfolio to 1,139 MW," Chief Executive Steve Snyder said in a statement.

Once completed, the facility will produce enough energy to power about 10,500 Quebec homes and is expected to generate about 100 jobs during the development and construction phases.

Last December, TransAlta added two wind facilities in Alberta and New Brunswick, ahead of schedule.

The company operates more than a third of Canada's installed 3,549 MW wind capacity.

Related News

ev

British Columbia Halts Further Expansion of Self-Driving Vehicles

VANCOUVER - British Columbia has halted the expansion of fully autonomous vehicles on its roads. The province has announced it will not approve any new applications for testing or deployment of vehicles that operate without a human driver until it develops a new regulatory framework.


Safety Concerns and Public Questions

The decision follows concerns about the safety of self-driving vehicles and questions about who would be liable in the event of an accident. The BC government emphasizes the need for robust regulations to ensure that self-driving cars and trucks can safely share the road with traditional vehicles, pedestrians,…

READ MORE
integrating-ai-data-centers-into-canadas-electricity-grids

Integrating AI Data Centers into Canada's Electricity Grids

READ MORE

power blackout

Study: US Power Grid Has More Blackouts Than ENTIRE Developed World

READ MORE

Substation Maintenance Training

Substation Maintenance Training

READ MORE

Quebec Halts Crypto Mining Electricity Requests

READ MORE