Colorado utility's rebuff of Wyoming wind surprises


Protective Relay Training - Basic

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 12 hours Instructor-led
  • Group Training Available
Regular Price:
$699
Coupon Price:
$599
Reserve Your Seat Today
A Colorado utility's rejection of southeast Wyoming wind power as part of its energy supply doesn't negate the need for wind development or new transmission lines in the region, Wyoming supporters said.

Xcel Energy released an evaluation last month of bids it received in response to a request for proposals to add nearly 1,000 megawatts of renewable energy for Colorado customers through 2015.

Wyoming wind and infrastructure developers were surprised to learn that Xcel's report rejected all bids from wind developers in southeast Wyoming.

Trans-Elect Development Company and the Wyoming Infrastructure Authority were among the parties that promoted Wyoming wind to Xcel.

The two are working together to develop the Wyoming-Colorado Intertie transmission project, a $3 million, 850-megawatt line proposed to run from southeast Wyoming to Colorado's populous front range. LS Power and the Western Area Power Administration are also involved in the project.

The two are working together to develop the Wyoming-Colorado Intertie transmission project, a $3 million, 850-megawatt line that would run from southeast Wyoming to Colorado's populous front range. LS Power owns the proposed line.

"We're surprised and we're disappointed but this is just the first skirmish in a long-term campaign," said Jerry Vaninetti, Trans-Elect's vice president of western development. "We still believe in the fundamentals of the project."

Wyoming state government has promoted southeast Wyoming as ripe for wind development because of its strong winds, willing landowners and minimal environmental conflicts. However, there's a shortage of transmission capacity to export energy from southeast Wyoming to markets like Colorado cities.

Steve Ellenbecker, the Wyoming Infrastructure Authority's director of governmental and external relations, said the Wyoming-Colorado Intertie is meant to alleviate that "bottleneck."

"It's there and (Xcel's decision) doesn't become a dispute about that fact," Ellenbecker said. "There's a need for opening up a pathway for the exchange of power between Wyoming and Colorado in either direction."

For Xcel's purposes, the southeast Wyoming wind bids weren't better than Colorado wind bids, according to the company's report.

"SE Wyoming wind bids were higher priced than the most economic Colorado wind bids and provided generation pattern data that appears no more favorable to the overall system than NE Colorado wind," the report said.

The report found that the Wyoming wind bids were comparable to Colorado's in terms of capacity factor, or a wind farm's productivity compared to its maximum potential. The Wyoming bids ranged from capacity factors of about 36 percent to 42 percent, while Colorado's ranged from about 32 percent to 45 percent.

Xcel's report also found that northeast Colorado wind farms historically have had better generation patterns, meaning they produce more of their annual electricity from the hours of 9 a.m. to 6 p.m. than the Wyoming bids would have.

Ellenbecker said he had hoped Xcel would advance the Wyoming wind bids to serve as a catalyst for both southeast Wyoming wind development and the Wyoming-Colorado Intertie.

"It looks like the advantage went to the resources that had the shorter transmission difference as a significant potential factor," Ellenbecker said.

Backers of the Wyoming-Colorado Intertie are curious to see what happens during the next couple of months as the Colorado Public Utilities Commission reviews Xcel's selection of new power supply sources.

"We're hopeful that there's a possibility Wyoming wind could get reconsidered during this 90-day period," Vaninetti said. "We're all dependent upon buyers in Colorado in buying both wind and the transmission services to deliver the wind."

Bob Whitton, a Wheatland rancher and chairman of the Renewable Energy Alliance of Landowners, said Xcel's exclusion of Wyoming bids won't deter his group's members from pursuing wind development leases on their lands.

"We've got 800,000 acres of ground in southeast Wyoming that could produce way more power at a pretty high capacity factor than the Wyoming-Colorado Intertie could possibly handle," Whitton said. "So our question is not 'can we get on the Wyoming-Colorado Intertie?' The question is 'where is the rest of the transmission going to come from because we need a lot more?'"

Related News

California Welcomes 70 Volvo VNR Electric Trucks

Switch-On Project Electric Trucks accelerate California freight decarbonization, deploying Volvo VNR Electric rigs with high-capacity…
View more

The Haves and Have-Nots of Electricity in California

California Public Safety Power Shutoffs highlight wildfire prevention as PG&E outages disrupt schools, businesses, and…
View more

Six key trends that shaped Europe's electricity markets in 2020

European Electricity Market Trends 2020 highlight decarbonisation, rising renewables, EV adoption, shifting energy mix, COVID-19…
View more

Canada will need more electricity to hit net-zero: IEA report

Canada Clean Electricity Expansion is urged by the IEA to meet net-zero targets, scaling non-emitting…
View more

Alliant aims for carbon-neutral electricity, says plans will save billions for ratepayers

Alliant Energy Net-Zero Carbon Plan outlines carbon-neutral electricity by 2050, coal retirements by 2040, major…
View more

New York Finalizes Contracts for 23 Renewable Projects Totaling 2.3 GW

New York Renewable Energy Contracts secure 23 projects totaling 2.3 GW, spanning offshore wind, solar,…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.