TVA CEO expects Bellefonte nuclear to be reality

HUNTSVILLE, ALABAMA - TVA CEO Tom Kilgore said he expects the utility to announce a decision in August on whether it will complete the nuclear reactor at Bellefonte Nuclear Plant near Scottsboro or follow through on plans to build a new model reactor there.

In my opinion we will absolutely do something at Bellefonte, Kilgore said during a stop in Huntsville. Its not a question of if, but what.

TVA has estimated construction on Bellefontes Unit 1 reactor is about 90 percent complete.

TVA began the project in the 1970s and abandoned it and a second unit in the late 1980s due to budget pressures and cost overruns. The Bellefonte plant has cost TVA about $4.5 billion to date.

Cost estimates for the nextgeneration reactors vary, but projections have gone from about $7 billion for two reactors to as high as $17 billion.

TVA restarted the Unit 1 reactor at Browns Ferry in 2007, after it was dormant for 22 years, for about $2 billion.

Kilgore said completing the work at Bellefonte would be faster and less expensive than building newmodel reactors still under development by Westinghouse. He said there are things they like and dislike on both sides of the question.

With increased pressure on TVA to lower its carbon emissions and burn less coal, nuclear power is a preferred option, Kilgore said.

Area officials are optimistic about the Bellefonte project.

There are at least 200 engineers working out there today, doing research, studies... said Ron Bailey, vice president for business development at the Jackson County Chamber of Commerce. It was mothballed in 1988 and one reactor was 90 percent complete.

Were expecting it to be a go.

TVA has said it would like to be generating power at Bellefonte by 2018 to 2020.

Kilgore addressed a number of other issues Thursday:

• Power bills are likely to continue to rise, due to rising fuel costs, until midsummer, Kilgore said. He hopes that prices will level off at that point, but they are unlikely to go down by much. TVA began doing a monthly fuel cost adjustment to power bills last fall, instead of quarterly adjustments.

• TVA will spend some $250 million over the next several years to shore up and upgrade the coal ash retention facilities at its Widows Creek plant near Bridgeport. The utility will move from wet to dry storage of coal ash a byproduct of burning coal for electricity to help avoid spills like the devastating billiongallon spill in December 2008 near Kingston, Tenn.

• The utility wants to increase energy efficiency among its customers and is expected to announce a series of conservationfriendly incentives this year, Kilgore said. A recent TVA project to construct three homes using varying standards of energy efficiency saw a power bill difference of up to $100 a month, Kilgore said. The upfront costs were about $20,000 higher for the most energyefficient home.

Related News

hydro quebec dam

As Maine debates 145-mile electric line, energy giant with billions at stake is absent

BANGOR - As Maine regulators are deciding whether to approve the construction of a $1 billion transmission line across much of western Maine, the Canadian hydroelectric utility poised to make billions of dollars from the project has been absent from the process.

This has left both opponents and supporters of the line arguing about how much available energy the utility has to send through a completed line, and whether that energy will help fulfill the mission of the project: fighting climate change.

And while the utility has avoided making its case before regulators, which requires submitting to cross-examination and discovery, it has…

READ MORE

BLM Announces Completion of Crimson Energy Storage Project

READ MORE

solar power from space

How to Get Solar Power on a Rainy Day? Beam It From Space

READ MORE

severe winter and grid

Canadian Electricity Grids Increasingly Exposed to Harsh Weather

READ MORE

fortis

FortisAlberta Takes Necessary Precautions to Provide Electricity Service for Alberta

READ MORE