Rolling blackouts follow cable shutdown

BEDEQUE, PRINCE EDWARD ISLAND - A broken insulator at the Bedeque substation shut down one of the two cables that carries electricity to PEI from the mainland, leaving thousands without electricity.

The problem started at 6 p.m. and took about 3.5 hours for Maritime Electric to repair. At one point 23,000 households were without electricity.

While Maritime Electric has oil-fired generators on the Island, it is heavily reliant on the far less expensive power it can import via two cables under the Northumberland Strait. Those cables are close to capacity, and when one goes down, the electricity grid goes into a partial shutdown to protect the remaining cable.

"One of the things that can damage that type of equipment is overloading it," said Maritime Electric vice-president of corporate planning and energy supply John Gaudet.

"We want to make sure that we take care of them the best we can."

Maritime Electric was able to provide 30 MW of power from the Eastern Kings Wind Farm, saving it from firing up more generators.

"It just was good fortune that the wind was blowing," said Gaudet.

"It was a classic example of wind replacing oil."

The cables to the mainland were installed in 1977. At the time, either one could supply the entire province's needs, but that is no longer the case.

The province has been lobbying the federal government for funding for a new cable to the mainland, in part to export wind power produced on the Island.

Maritime Electric is continuing to investigate why the insulator at the Bedeque substation failed.

Related News

maine electrical worker

Construction starts on disputed $1B electricity corridor

PORTLAND - Construction on part of a $1 billion electricity transmission corridor through sparsely populated woods in western Maine is on hold because of legal action, but that doesn't mean all building has been halted.

Workers installed the first of 829 steel poles Tuesday on a widened portion of the existing corridor that is part of the project near The Forks, as the groundwork is laid for the 145-mile ( 230-kilometre ) New England Clean Energy Connect.

The work is getting started even though the 1st U.S. Circuit Court of Appeals delayed construction of a new 53-mile ( 85-kilometre ) section.

Three conservation…

READ MORE
drum fire

Failed PG&E power line blamed for Drum fire off Hwy 246 last June

READ MORE

nevada solar panels

Nevada on track to reach RPS mandate of 50% renewable electricity by 2030: report

READ MORE

IESO

Key Ontario power system staff may end up locked down at work sites due to COVID-19, operator says

READ MORE

damaged power grid

New Power Grid “Report Card” Reveal Dangerous Vulnerabilities

READ MORE