PMLD replacing old wind turbines
PMLD was developing the project with Community Energy Incorporated, which was acquired in 2006 by Iberdrola Renewables, a subsidiary of Grupo Iberdrola. However, Iberdrola withdrew from the project, deeming it too small and allowing PMLD to take control.
The city financed the $7.15 million project and selected Fuhrlander AG to provide two 1.5-megawatt FL-1500 wind turbine/generators. Lumus Construction Incorporated was selected to handle construction.
Civil site construction began in August 2007 off of Stage Coach Trail Access Road commenced. The turbines are expected to be delivered by Fuhrlander in April or May 2009. PMLD expects Lumus to complete construction and commissioning within 30 days of delivery. PLMD Manager Jonathan Fitch has said that the city might consider one or two more turbine/generator sites after this project is complete.
Related News

Site C dam could still be cancelled at '11th hour' if First Nations successful in court
VANCOUVER - The Site C dam could still be stopped by an "eleventh hour" court ruling, according to the lawyer representing B.C. First Nations opposed to the massive hydroelectric project near Fort St. John.
The B.C. government, BC Hydro and West Moberly and Prophet River First Nations were in B.C. Supreme Court Feb. 28 to set a 120-day trial, expected to begin in March 2022.
That date means a ruling would come prior to the scheduled flooding of the dam's reservoir area in 2023 said Tim Thielmann, legal counsel for the West Moberly First Nation.
"The court has left itself the opportunity for…