Judge orders Duke power plant shutdowns


NFPA 70E Training - 2027 Edition - Arc Flash and Electrical Safety Course

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 6 hours Instructor-led
  • Group Training Available
Regular Price:
$199
Coupon Price:
$149
Reserve Your Seat Today
Judge Larry McKinney issued a ruling in U.S. District Court for the Southern District of Indiana calling for Duke Energy to shut down three units at the companyÂ’s West Terre Haute Wabash River Station no later than September 30.

The majority of the plant’s capacity is unaffected by the ruling, which calls for units 2, 3 and 5 to be retired, while the remaining Duke Energy-owned units at the station – 4 and 6 – will be unaffected. Shutting down units 2, 3 and 5 will remove a combined capacity of 265 megawatts, which is 39 percent of the station’s 677- megawatt power generating capacity.

Following an adverse ruling by a jury in May 2008, Duke Energy had proposed as a remedy that units 2, 3 and 5 be retired in 2012, when the new IGCC plant in Edwardsport comes on line. The courtÂ’s order today accelerates that timetable by two years.

“We are disappointed with the court’s decision to accelerate the shutdown of Wabash River Units 2, 3 and 5,” said Duke Energy Chief Legal Officer Marc Manly. “But even though disappointed, I will reiterate our satisfaction that after 10 years of litigation, the company’s position regarding power plant projects was vindicated in the vast majority of instances about which the government originally complained. We will continue to review the Court’s ruling and evaluate our options.”

The judge also ruled:

• The company will not have to install additional emissions reduction equipment on units 4 or 6.

• Duke Energy will have to surrender sulfur dioxide (SO2) allowances for the period between May 22, 2008 and Sept. 20, 2009. This amount is significantly less than requested by the government.

• Judge McKinney reduced the government’s proposed fine on Beckjord Station from $1.32 million to $687,500.

“The units at Wabash River impacted by this decision are more than 50 years old," said James L. Turner, president and chief operating officer of Duke Energy’s Franchised Electric & Gas segment. “This order should not have an impact on Duke Energy’s operation in 2009 because of changes we already made to our operating plans following the jury’s verdict last summer. However, we will have to re-evaluate our plans for meeting peak demand the next two summers and work with the Midwest Independent System Operator to ensure we have an adequate plan for the reliable operation of the system.”

In addition to the new coal gasification plant, Duke Energy will have invested nearly $5 billion to substantially reduce emissions of sulfur dioxide, nitrogen oxide and other pollutants from the companyÂ’s coal-based power plants in the five states it serves. The net result of these investments will be a reduction of sulfur dioxide and nitrogen oxide emissions by approximately 70 percent across Duke EnergyÂ’s five-state service area by 2010.

Duke Energy IndianaÂ’s operations provide 6,500 megawatts of electricity capacity to approximately 775,000 customers, making it the stateÂ’s largest electric supplier.

Related News

For Hydro-Québec, selling to the United States means reinventing itself

Hydro-Quebec hydropower exports deliver low-carbon electricity to New England, sparking debate on greenhouse gas accounting,…
View more

Quebec Halts Crypto Mining Electricity Requests

Hydro-Quebec Crypto Mining Pause signals a temporary halt as blockchain power requests surge; energy regulator…
View more

OEB issues decision on Hydro One's first combined T&D rates application

OEB Hydro One Rate Decision 2023-2027 sets approved transmission and distribution rates in Ontario, with…
View more

Will Israeli power supply competition bring cheaper electricity?

Israel Electricity Reform Competition opens the supply segment to private suppliers, challenges IEC price controls,…
View more

Recommendations from BC Hydro review to keep electricity affordable

BC Hydro Review Phase 2 Recommendations advance affordable electricity rates, clean energy adoption, electrification, and…
View more

Melting Glass Experiment Surprises Scientists by Defying a Law of Electricity

Electric Field-Induced Glass Softening reveals a Joule heating anomaly in silicate glass, where anode-side nanoscale…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified