The Potomac-Appalachian Transmission Highline (PATH), a 765-kilovolt line extending from southwestern West Virginia to central Maryland, now has a June 2014 completion deadline. The one-year schedule change results from a recent reliability analysis by PJM Interconnection (PJM) that considered various factors, including its 2009 load forecast.
PJM, the regional grid operator directing the construction of PATH, has confirmed that the project remains critical to addressing regional reliability concerns. PJMÂ’s latest update of its reliability analysis confirms that significant overloads and voltage problems will occur in the region, beginning in 2014, if the PATH project is not completed.
The PATH project team expects to file applications for approval to build the line with the West Virginia, Maryland and Virginia regulatory commissions in the second quarter. Timely approvals by the state commissions are needed to meet the new deadline established by PJM.
Related News
Northvolt Affirms Continuation of EV Battery Plant Project Near Montreal
How utilities are using AI to adapt to electricity demands
NB Power signs three deals to bring more Quebec electricity into the province
Shell says electricity to meet 60 percent of China's energy use by 2060
Sask. Party pledges 10% rebate on SaskPower electricity bills
Pandemic has already cost Hydro-Québec $130 million, CEO says
Sign Up for Electricity Forum’s Newsletter
Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.
Electricity Today T&D Magazine Subscribe for FREE
- Timely insights from industry experts
- Practical solutions T&D engineers
- Free access to every issue