Wave-energy project halted

subscribe

A small wave-energy project off Washington's northwest coast won't be built after its British Columbia-based developer decided to halt all wave-energy projects and focus instead on wind power.

The one-megawatt project planned for Makah Bay in the Olympic Coast National Marine Sanctuary was the country's first wave-energy project to receive an operating license. Its developer, Finavera Renewables, also pulled permits for a larger project it had planned off the Northern California coast.

Such projects use buoys equipped with turbines that harness the power of the rolling waves to generate electricity.

Finavera declined to comment about why it decided to give up its wave-energy projects, but officials said its most pressing concern is finishing a handful of wind projects in Canada and Ireland.

The company's wave-power buoy sank unexpectedly during a test run more than a year ago off the Oregon coast, and the plans to place four buoys in Makah Bay have lagged because of state and federal permitting.

Finavera's decision isn't surprising given the wave-energy industry's infancy compared with wind, which now has honed its turbine technology and lowered power costs, said Roger Bedard, ocean-energy leader with the nonprofit Electric Power Research Institute.

Bedard said he was optimistic that wave-device testing and planned commercial projects by different companies and Oregon State University off the Oregon coast will propel the young field forward.

Related News

Chief Patrick Michell

Independent power project announced by B.C. Hydro now in limbo

VANCOUVER - A small run-of-river hydroelectric project recently selected by B.C. Hydro for a power purchase agreement may no longer be financially viable.

The Siwash Creek project was originally conceived as a two-megawatt power plant by the original proponent Chad Peterson, who holds a 50-per-cent stake through Green Valley Power, with the Kanaka Bar Indian Band holding the other half.

The partners were asked by B.C. Hydro to trim the capacity back to one megawatt, but by the time the Crown corporation announced its approval, it agreed to only half that — 500 kilowatts — under its Standing Order clean-energy program.

“Hydro wanted…

READ MORE
china solar panel manufacturing

China's electric power woes cast clouds on U.S. solar's near-term future

READ MORE

coal pile

New England Emergency fuel stock to cost millions

READ MORE

BC Hydro cryptic about crypto mining electricity use

READ MORE

texas line crew performs repairs

Texas lawmakers propose electricity market bailout after winter storm

READ MORE